Case Background
A lithium company operates a 4.6×72m rotary kiln fueled by natural gas, equipped with a clean-air fan of 114 Nm³/min at 29.4 kPa. Design output is 850–1100 t/h; natural gas calorific value is 8300 kcal/Nm³, with normal usage 300–3600 and maximum 4500. During this commissioning, kiln feed was 54 t/h—essentially full capacity. Main equipment and process parameters are shown below.
At the start of commissioning, the kiln had heavy dust, turbidity, large lumps, and local material melting. Although production could be maintained, kiln stability and clinker quality were at risk.
| Parameter | Value |
|---|---|
| Kiln specification | 4.6×72m |
| Design output | 850–1100 t/h |
| Fuel | Natural gas, calorific value 8300 kcal/Nm³ |
| Clean-air fan | 114 Nm³/min, 29.4 kPa |
| On-site feed | 54 t/h (essentially full capacity) |
Problem Analysis
Slow kiln speed: Low speed caused excessive material residence time and a thicker bed, worsening kiln permeability—a major cause of dust and lumps.
Improper flame position: The flame concentrated on a local area, causing local overheating and material melting.
Insufficient air matching: Inadequate negative pressure and permeability made dust hard to discharge, keeping the kiln turbid long-term.
Commissioning Measures
The 5-day commissioning optimized kiln parameters for on-site conditions through a comprehensive approach, achieving the goals via close cooperation with on-site operators.
After commissioning, large lumps decreased markedly, dust conditions improved, and crusher current dropped. Kiln speed rose from 0.77 to 1.05 r/min, conversion reached 98.1%, consecutive assays were qualified, and kiln conditions improved noticeably and stabilized.
Commissioning Results
Quality improved: Qualified assays for two consecutive days; conversion rate reached 98.1%.
Kiln conditions improved markedly: Large lumps decreased significantly, dust conditions improved, crusher current dropped, and kiln conditions stabilized.
Kiln speed effectively increased: Kiln speed rose by about 36%, significantly shortening material residence time.
The 5-day commissioning raised kiln speed by ~36%, with conversion reaching 98.1% and consecutive qualified assays—validating Zhonghe's combustion system adaptability and the after-sales team's rotary kiln burner expertise. Backed by thousands of projects, Zhonghe precisely troubleshoots to stabilize kiln conditions, ensure quality, and achieve efficient, low-consumption production.